Monday, December 3, 2007
Project Narrative
The existing structure presented some significant planning difficulties in that it is a long rectangular building with single span timber beams spanning in the short direction. The north-south orientation of this building also presented major problems in terms of introducing natural light whilst eliminating hot west sun. Furthermore the elimination of all internal cross walls created a major problem for structural bracing of the building.
The zig-zag plan form, which ultimately was devised for the project, assisted in addressing a multitude of problems. Firstly the new segments of building created the potential for raised lantern roof structures at 45o to the main north-south axis thus enabling the entry of light to the western half of the building from the east. Furthermore the zig-zag profile enabled windows to be installed on the south-west side thus preventing exposure to direct west sun. In functional terms, the zig-zag configuration also gave the opportunity to create individual group zones slightly separated from adjoining zones and yet having access to a main central spine. The zig-zag configuration also gave the opportunity for a main entry to the College with verandah and signage at the southern entry point. It was hoped that this would encourage after-hours use of the Centre and would improve community access. An existing enclosed court at the north end of the complex, previously used as a
In economic terms, the building has achieved possibly one of the largest Flexible Learning Centres in
In environmental terms, significant efforts have been made to minimise energy consumption in this building. Natural light is achieved through the new lantern roofs thus making the building very light internally despite its existing flat roof and limited west windows. Furthermore, the zig-zag profile of the west wall has enabled windows to be oriented to the south-west thus eliminating excessive heat gain. The building is extensively insulated and components from the existing building have been used as much as possible.
Project Initiated | AUGUST 2004 |
Education Specification | APRIL 2005 |
Masterplan Started | APRIL 2005 |
Masterplan Completed | 8 JULY 2005 |
Schematic Design Started | APRIL 2005 |
Schematic Design Completed | 5 OCTOBER 2005 |
Schematic Design Cost Estimate | 5 OCTOBER 2005 |
Design Development Started | 5 OCTOBER 2005 |
Design Development Completed | 5 NOVEMBER 2005 |
Design Development Cost Estimate | 5 NOVEMBER 2005 |
Construction Documents Completed | 25 JANUARY 2006 |
Tender Estimate Cost | 28 FEBRUARY 2006 |
Tender Acceptance Cost | 1 MARCH 2006 |
Construction Started | 8 MARCH 2006 |
Construction Completed | 23 AUGUST 2006 |
Occupancy | 23 AUGUST 2006 |
Post Occupancy Evaluation | NOT YET DONE |
Project Cost : AUD$ 613,921 |
Facility Cost : AUD$ 549,357 |